Many nuclear plants can improve their economic
performance. Analysis shows a large spread between the nuclear plants
with the highest costs and those with the lowest costs. The plants in
the high-cost quartile spend twice as much on O&M and fuel as the
plants in the low-cost quartile. The higher-cost units clearly have a
significant opportunity to improve efficiency and reduce costs.
The positive outlook for U.S. nuclear power plants is
in stark contrast to speculation several years ago—when industry
restructuring at the state level was just beginning and competitive
markets were in their infancy-that many nuclear units would not be
economic and would be shut down prematurely. Since then, the
performance of the nuclear units has improved dramatically; the cost
of electricity from other sources has increased; and surplus
generating capacity in most regions of the country has all but
disappeared. Today, virtually all nuclear units are expected to
operate to the end of their 40-year licenses, and most will renew
their licenses for an additional 20 years.
A generating company with nuclear power in its
portfolio must decide whether to continue to operate its nuclear
unit(s), or shut down its nuclear capacity and build new, replacement
capacity. In today's market, that replacement capacity would be a
gas-fired combined cycle power plant. A well-managed nuclear unit can
produce electricity profitably at a total cost of 2.0-2.5 cents per
kilowatt-hour. A new gas-fired plant would produce electricity at a
total cost of 3.5-4.5 cents per kilowatt-hour, assuming a plant
capital cost of $500-600 per kilowatt and gas prices of $3-4 per
million Btu. The choice is clear: companies may build new gas-fired
capacity to meet new growth in electricity demand, but they would not
close an existing nuclear unit and replace it with a new gas-fired
power plant.
In addition to their value as reliable producers of
low-cost bulk electricity, existing nuclear units have substantial
additional value because of trends in the fossil fuel markets. The
existing nuclear plants represent:
Nuclear power plant operating and maintenance
(O&M) costs increased, on average, by 7-8 percent a year above
inflation through much of the 1980s. In 1986-1987, for the first time
ever, the average production cost from nuclear plants exceeded that of
coal-fired plants. (Production cost consists of O&M plus fuel.)

Since then, nuclear plant O&M costs have leveled off and
decreased.
Recent Trends
Nuclear plant operators pursued several initiatives to reduce O&M
costs. More comprehensive planning and innovative management
techniques have reduced the time that nuclear power plants are out of
service for refueling. In 1990, the average duration for a refueling
outage at U.S. nuclear power plants was 101 days. Since then, that
figure has dropped steadily. In 1999, the average outage was 41.5
days, and the top performers are recording refueling outages of 25
days or less.
This and other improvements have resulted in substantial increases in
the amount of electricity produced by the plants.
| n |
In 1990, 56 nuclear units had capacity factors above 70 percent;
31 units operated above 80 percent. |
| n |
In 1999, 98 of 103 units had capacity factors above 70 percent; 90
units operated above 80 percent. |
Thanks to improved management practices, higher reliability and
output, and shorter refueling outages, the average production cost
(O&M plus fuel) of electricity from U.S. nuclear power plants has
declined since the mid-1980s—a 45 percent decrease since 1987, when
average nuclear production costs peaked at 3.12 cents per
kilowatt-hour.
Nuclear plant operators are also reducing capital spending. Capital
requirements at operating nuclear plants have dropped
dramatically—from $60-$70 per kilowatt per year in the mid-1980s to
$20-$30 per kilowatt in the early 1990s. Most nuclear units are
projecting incremental capital requirements of approximately $10-$15
per kilowatt going forward.
Opportunities for Improvement in Economic
Performance
Many nuclear plants should be able to improve their economic
performance even further.
Analysis shows a large spread between the nuclear
power plants with the highest costs and those with the lowest costs.
The nuclear plants in the low-cost quartile had an average production
cost (O&M plus fuel) of 1.33 cents per kilowatt-hour in the
1997-99 period. The plants in the high-cost quartile had an average
production cost of 2.8 cents/kWh—more than twice as high.
The plants in the second and third quartiles had
average production costs of 1.58 cents/kWh and 1.84 cents/kWh,
respectively.
(The units with the lowest O&M costs tend to be
among the most efficient units, with high capacity factors and
superior performance ratings from the Nuclear Regulatory Commission
and the industry.)
While there is still room for the lower-cost plants to
improve, there is a significant opportunity for the higher-cost units
to improve efficiency and reduce costs dramatically.
For the plants in the third and fourth
quartiles—and, to an extent, those in the second quartile—the
obvious challenge is finding ways to improve economic performance to
the level achieved by the plants in the first quartile.
Although the larger plants-simply because they can
produce more electricity-are generally better-positioned for
competition, analysis shows that smaller plants can also operate
safely and reliably at low cost.
Consolidation
As competition develops and industry restructuring unfolds, electric
power companies across the country are making strategic business
decisions.
Some companies are divesting power generation assets
and focusing on transmission and distribution. Some are divesting
generation in their traditional service territory, but buying
generation elsewhere. All companies are evaluating the economics of
their power plants, including future capital needs, to determine
whether those plants can survive in a competitive market.
This new business approach is also at work in the
nuclear energy sector. Some companies are divesting nuclear assets.
Others are buying.

The transition to greater competition in electricity
generation is leading to formation of new corporate entities, such as
large nuclear operating companies. By focusing resources solely on
nuclear power operations, such restructurings will enhance nuclear
power plant reliability, safety performance and, in parallel, economic
performance.
Evaluating the Competitive
Position of Nuclear Plants
Operating Economics
Few exercises are as complex as evaluating the competitive
position of a nuclear power plant (or, indeed, any power plant), and
making judgments about whether a given plant is economic or not.
Any such assessment, however, should proceed from
certain basic facts:
Existing power plants, including nuclear units, will
compete solely on the basis of operating economics, which do not
include sunk capital costs. As the electric power industry is
restructured, recovery of invested capital is handled separately,
usually through some form of separate "transition charge."
Production costs (O&M plus fuel) do not represent
the complete cost of electricity produced by a nuclear power plant,
and are thus not a definitive indicator of its ability to compete. A
nuclear plant must be able to compete on the basis of total
cost—production cost plus ongoing capital requirements plus general
and administrative (G&A) expenses. (G&A expenses typically
include property taxes.)
A number of nuclear power plants built in the 1980s
cost considerably more than originally estimated—a product of oil
supply and price disruptions in the 1970s, which led to double-digit
inflation, slower economic growth and reduced growth in electricity
demand.
In addition, after the accident at Three Mile Island
in 1979, nuclear plants were swamped by new regulatory requirements,
and forced to undergo extensive redesign to incorporate lessons
learned from the accident. These design changes for plants still under
construction, coupled with licensing delays, resulted in long,
drawn-out construction schedules. On average, it took 10.5 years
during the 1980s to build a nuclear power plant in the United States
and get it into operation. (By contrast, it takes four to five years
to build a nuclear power plant in France, Japan and other
industrialized countries.)
To make matters worse, many of these plants were being
built at a time of double-digit inflation, when interest rates on
borrowed money were very high. As the electric power industry is
restructured, these and other categories of "stranded costs"
are being recovered—in whole or in part—through special transition
charges. The stranded costs associated with nuclear power plants will
not affect the cost of electricity produced by those plants.

Other Factors
Cost is not, however, the sole determinant of whether a nuclear unit
will be able to compete. Other factors can have a significant effect
on the market value of a nuclear power plant, including:
|
n |
whether there is surplus
generating capacity in a region and, if there is, how long that
surplus is expected to last; |
|
n |
clean air constraints that will drive up the cost
of increasing electricity production from existing coal-, gas- or
oil-fired capacity, or possibly preclude increasing output from
existing fossil fuel-fired capacity or building new plants that
burn fossil fuels; |
|
n |
transmission constraints into the region, which
may limit the amount of power that can be imported and thus
increase the value of in-region generation; and whether the
nuclear unit provides essential "ancillary services" and
is important to maintaining the stability and reliability of the
transmission system. |

Natural Gas Price Volatility, Clean Air
Compliance: Added Value for Nuclear Generation
In addition to their
value as reliable producers of low-cost bulk electricity, existing
nuclear units have substantial additional value because of trends in
the fossil fuel markets. The existing nuclear plants represent:
| n |
A valuable hedge against volatility in the natural
gas market. Natural gas prices to electric generators have doubled
over the last 12 months, which has had a major impact on the cost
of electricity produced by gas-fired power plants. Nuclear units
provide a high level of forward price stability, because their
operating costs are predictable and stable. In volatile
electricity markets, this price stability has value to buyers. |
| n |
Valuable protection against escalating
environmental requirements and clean air constraints, which will
drive up the cost of increasing electricity production from
existing coal-, gas- or oil-fired capacity, or possibly preclude
increasing output from existing fossil fuel-fired capacity or
building new plants that burn fossil fuels. |
Natural Gas Prices
After several years of low wellhead prices (in the $2.25-2.50 per
million Btu range), U.S. natural gas prices started to increase
rapidly early in 2000. The rapid escalation in gas prices was largely
caused by gas demand (particularly in the electric generation sector)
beginning to outstrip supply. Several years of low wellhead gas prices
had depressed domestic exploration and production for natural gas.
Gas prices to electric
generators have increased substantially. The Energy Information
Administration now projects the average cost of gas for power
generation this year will be $3.99 per million Btu, a significant
increase from the $2.57-per-million-Btu average in 1999. Prices to
electric generators are up significantly in all regions of the
country.
Drilling for gas has increased sharply in response to
higher prices: the number of rigs drilling for gas in the United
States has risen to over 800, 45-50 percent higher than a year ago.
Even so, it will take 12-18 months to bring new supplies to market,
and consensus forecasts indicate that higher natural gas prices will
persist through 2001.
Even
if and when gas prices moderate, most analysts expect the price
volatility to continue, and believe that natural gas will behave like
all commodities (including electricity): (1) higher gas prices will
prompt more drilling and more production; (2) production will outrun
demand, forcing prices down again, although probably not down to
previous lows; (3) lower prices will drive up demand until demand
outruns supply; and (4) the cycle will repeat.
The sharp increase in gas prices this year has a significant impact on
the cost of electricity produced by gas-fired power plants because
these plants are extremely sensitive to changes in fuel price.
Approximately two-thirds of the cost of electricity from a new
combined-cycle gas plant is fuel cost.
Clean Air Compliance
Power plants burning fossil fuels, particularly coal-fired plants, are
subject to heavy and increasing regulatory and enforcement burdens
under a Clean Air Act that has become steadily more complex and
intrusive over the past 25 years. The cumulative impact of
increasingly restrictive clean air requirements will be costly—both
in terms of additional investment in equipment and increased operating
costs—and will almost certainly increase the relative attractiveness
of non-emitting sources like nuclear energy.
The cost of air pollution
control is already high, and likely to get higher. From 1987 through
1994, electric utilities' spending for clean air compliance doubled,
increasing from $3 billion to $6 billion in 1994 (constant 1993
dollars). This represents a real annual growth rate of 10 percent over
that period—an extraordinarily high rate of real, sustained growth
compared to other economic indicators.
Looking to the future, one
recent analysis shows that U.S. power companies1 clean air compliance
costs will increase from $6.6 billion in 1995 to $11.4 billion in
2000. In fact, since the year 2000 marks the start of Phase II of the
1990 Clean Air Act's acid rain program, it is likely that air
pollution costs in the early years of the 21st century will increase
more rapidly than in the 1995-2000 period. Another recent analysis
projects the cost of meeting new EPA air quality initiatives at $21.8
billion over the next 10-15 years2.
At the very least, existing and emerging clean air
requirements will tend to drive up the cost of coal-, gas- and
oil-fired generation, possibly by a significant amount, and thus make
existing nuclear power plants more competitive.
|
1.
|
Costs Incurred by the Electric Utility Industry
due to Federal Air Pollution Control Requirements, by Management
Information Systems, Inc. for the Edison Electric Institute, July
1996. |
|
2.
|
At What Cost? Federal Environmental Regulations in
a Competitive Marketplace; analysis by Resource Data International
for the Edison Electric Institute, June 1998. |
Transportation Container
Testing Films
In all of the following tests conducted by U.S. DOE
Sandia National Laboratories, used nuclear fuel transportation
containers retained their integrity and would have kept their
radioactive cargo locked safely inside.
Back to Business of Nuclear
home